Crossrail might not open to passengers until 2021, more than two years after services were originally due to commence, it has been reported.

A senior source associated with the new railway line beneath London told the BBC the “best-case scenario” would be the new link opening in spring 2020.

A “middle probability case” would be the summer of 2020, while a “worst case is the spring of 2021”.

Known as the Elizabeth Line, the subterranean railway between Reading in Berkshire and Shenfield in Essex was originally planned to open in December 2018.

The source told the BBC that testing of trains and signalling was “proving more difficult than was first thought”.

“It all depends on how dynamic testing goes between now and the end of this year,” they said.

“The last quarter of this year will be a critical period for the testing.”

Crossrail said London needs the Elizabeth Line to be “completed as quickly as possible and brought into service for passengers”.

“We are working very hard to finalise our new plan to deliver the opening at the earliest opportunity and we will be providing more details later this month.”

The scale of the potential delays was reported after an influential group of MPs demanded the project’s failures are explained by the Government.

Passengers had not been told the root causes for the railway being delayed and over budget, a scathing report by the Commons’ Public Accounts Committee (PAC) stated.

The cross-party committee urged the Department for Transport (DfT) to make clear what it, Transport for London and Crossrail Ltd are responsible for in relation to the project.

(PA Graphics)
(PA Graphics)

Committee members warned they were “not convinced” that trains would begin running in 2020 or that the “additional £2.8 billion of funding provided will be enough”.

The DfT was also accused of failing to put in place robust governance arrangements.

Crossrail’s cost is being met by the Government, the Greater London Authority – including TfL – and London businesses.

Crossrail Ltd, a wholly-owned subsidiary of TfL, was established in 2001 to build the new railway.

Crossrail poster
Sources have said Crossrail might not open until 2021 (John Stillwell/PA)

The project’s budget has fluctuated from £15.9 billion in 2007 to £14.8 billion in 2010.

But due to the cost of the delayed opening, a £2 billion Government bailout of loans and cash was announced in December.

Labour MP Meg Hillier, who chairs the PAC, said passengers have been “badly let down” and it is clear the planned opening date was “unrealistic for some time”.

Gail Cartmail, assistant general secretary of the Unite union, said: “The delays and cost overruns at Crossrail are totally unacceptable. This is a public project, funded by the taxpayer and money should have been used efficiently.

“Going forward it is essential that the lessons about poor industrial relations, which have undoubtedly led to problems and delays on the project are not repeated.”

A DfT spokesman insisted it “consistently challenged the leadership of Crossrail Ltd” on the delivery of the project.