COVID-19 has not stopped work to repair thousands of potholes in Ludlow and south Shropshire.

More than 3,300 potholes and other defects have been treated on Shropshire Council’s roads as the council’s highways team takes advantage of the reduction in traffic during the lockdown.

Up to April 23, 3,343 defects were treated.

The vast majority are pothole repairs, with work also including some kerbing and ironworks.

On average 37 work crews are on the county’s roads each day, predominately two-man pothole crews.

Work being carried out also includes texpatching, thermal patching, and jet patching.

“These figures show that we’re working hard to fix Shropshire roads,” said Steve Davenport, Shropshire Council’s cabinet portfolio holder for highways.

“We’re prioritising essential repairs, such as potholes and pavement defects, to ensure that the county’s roads remain safe and serviceable.

“This means that work is continuing to take place on the network, and we’re ensuring that council staff and contractors are following the Government guidelines – to ensure their health and safety, and that of the public.

“We’re also aware that the impact on the public is significantly reduced by undertaking highways work during this period and, as a result, we’re maximising our resources wherever possible.

“I’d like to thank all of our highways officers and contractors for carrying out this important work during what it a difficult time.”

Meanwhile, a limited number of highways schemes have been progressed or completed in recent weeks, but all planned and non-safety critical highway works are currently suspended – though will restart once the current restrictions are lifted.

Roads inspections have been largely unaffected, and all work is being monitored to ensure that it complies with Government guidelines say Shropshire Council.